Solved

Which of the Following Is a Step in Calculating the Early

Question 54

Multiple Choice

Which of the following is a step in calculating the early start dates of subsequent activities, assuming finish-start relationships?


A) Add the predecessor activity's duration to its finish date.
B) Refer to the resource calendar that applies to the people and equipment necessary for the activity.
C) Add the lead time or subtract the lag time.
D) Deduct the number of off-days that the activity would span on the resource calendars.
E) Assign the calculated date as the early start date of the predecessor activity.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions