Multiple Choice
Which of the following is a step in calculating the early start dates of subsequent activities, assuming finish-start relationships?
A) Add the predecessor activity's duration to its finish date.
B) Refer to the resource calendar that applies to the people and equipment necessary for the activity.
C) Add the lead time or subtract the lag time.
D) Deduct the number of off-days that the activity would span on the resource calendars.
E) Assign the calculated date as the early start date of the predecessor activity.
Correct Answer:

Verified
Correct Answer:
Verified
Q49: The higher levels of the work breakdown
Q50: The _ is the process of determining
Q51: Work performed on the project that consumes
Q52: Activities that have predecessor-successor relationships occur _.<br>A)
Q53: Float, sometimes called _, is the amount
Q55: An) _ has no duration or resources,
Q56: Lead time is _.<br>A) the amount of
Q57: An estimate is an educated guess based
Q58: The additional time added to the schedule
Q59: An updated schedule that shows the present