Multiple Choice
All of the following steps, as paraphrased by Tom Mochal, have the necessary components of a change documentation process EXCEPT:
A) inform project stakeholders of the change request process.
B) require that the change request be made in writing.
C) estimate the time needed to evaluate the change.
D) evaluate the change and its impact on the schedule.
E) withhold the distribution of the scope change log to team members .
Correct Answer:

Verified
Correct Answer:
Verified