Multiple Choice
The transition from planning to project initiation is typically marked by the decision to _____ the project and the _____ of the project manager.
A) approve; consideration
B) proceed with; assessment
C) support; training
D) commit to; evaluation
E) fund; selection
Correct Answer:

Verified
Correct Answer:
Verified