Multiple Choice
The DPCI score for size indicates the lowest level of complexity when:
A) the project size is at the high or low end of the range of project sizes that the organization or team members have done before.
B) the project management tools and processes will have to be adjusted and it is not certain that they will work well.
C) neither the organization nor the team members are experienced working on a project this size.
D) the project size is about 20 percent higher or lower than projects the organization or some of the team members have done before.
E) the project manager and team members have done many similar size projects and the tools they use to manage this size project are well tested and reliable.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Project documents are archived during the _
Q2: With reference to organizational complexity, when the
Q3: The _ represents the number of people
Q4: Which of the following statements is true
Q6: A score of _ in the Darnall-Preston
Q7: With reference to the technological complexity of
Q8: With reference to technology newness, the DPCI
Q9: The project quality manager focuses on the
Q10: The DPCI rating of 5 for technology
Q11: The _ Index ranks complexity in four