Multiple Choice
Which of the following statements is true regarding the Darnall-Preston Complexity Index DPCI) ?
A) The DPCI groups ten project attributes into four broad categories.
B) The categories of the DPCI are internal attributes, external attributes, technological complexity, and system scope.
C) The DPCI helps in defining the experience, knowledge, skills, and abilities needed by the project manager.
D) The DPCI has the tendency to further complicate the process of developing a project execution plan.
E) The DPCI has little impact on the composition and organization of the project leadership team.
Correct Answer:

Verified
Correct Answer:
Verified
Q39: Briefly describe the four categories of the
Q40: Which of the following statements is NOT
Q41: Institutions of higher learning and most government
Q42: Which of the following statements is true
Q43: The ecology includes the sights and sounds
Q45: Internal attributes:<br>A) are within the control of
Q46: Projects have the potential to impact the
Q47: External project attributes include those issues that
Q48: Project managers have always been assigned to
Q49: Even though all projects are unique, they