Multiple Choice
Which of the following statements is true regarding organization complexity as an attribute that contributes to project complexity?
A) Organizational complexity and project complexity are inversely related to one another.
B) The client team approach of handling projects reduces project complexity.
C) Projects with a team representing the client require less of the project manager's time and energy.
D) A project with one client as the central point for all information has a streamlined communication process.
E) The client team approach brings more expertise but often less comprehensive project oversight as well.
Correct Answer:

Verified
Correct Answer:
Verified
Q49: Even though all projects are unique, they
Q50: The _ attributes include those issues that
Q51: _, the greater the stress and the
Q52: Research by the Construction Industry Institute indicated
Q53: Ordered systems tend to be heterogeneous.
Q55: _ is an internal project attribute that
Q56: _, the more stress that is placed
Q57: Projects are usually _ systems, that is,
Q58: The purpose of the change management process
Q59: Institutions of higher learning have goal-based cultures.