The Conceptual Estimate Is Developed with the Least Amount of Knowledge

Question 61

Multiple Choice

The conceptual estimate is developed with the least amount of knowledge. When more information is known, the project team can develop a _____.


A) work breakdown structure
B) critical estimate
C) rough order of magnitude ROM) estimate
D) scope of work
E) ballpark estimate