A Project Budget Estimate Which Is Developed with the Least

Question 37

Multiple Choice

A project budget estimate which is developed with the least amount of knowledge is known as a _____.


A) rough order of magnitude ROM) estimate
B) scope of work
C) conceptual estimate
D) line estimate
E) milestone schedule