Multiple Choice
To bid on a job,Budget Construction Company relies on the oral promise of Coldwater Plumbing,Inc. ,to perform certain work at a certain price.Coldwater fails to per?form.Budget can
A) not recover due to the principle of freedom of contract.
B) not recover due to the Statute of Frauds.
C) recover under the concept of unconscionability.
D) recover under the doctrine of promissory estoppel.
Correct Answer:

Verified