Multiple Choice
Superior-Plus Properties, Inc., and Topps Construction Company sign a contract that specifies the amount to be paid. Additional compensation may be jus?tified by
A) any business risks that occur after the time of the contract.
B) changes in the market price of needed materials during the contract.
C) extraordinary difficulties unforeseen at the time of the contract.
D) no circumstances.
Correct Answer:

Verified
Correct Answer:
Verified