GroundSwell Pools,Inc. ,agrees to build a swimming pool for Francis,but fails to complete the job.Francis hires EquiAqua,Inc. ,to finish the project.Francis may recover from GroundSwell
A) the contract price less costs of materials and labor.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.