The Miller Manufacturing Company collected the following information (in days)for April and May.  April  May  Transporting product 2.03.0 Processing product 14.016.0 Inspecting product 0.50.8 Storing product 8.05.0\begin{array} { | l | r | r | } \hline & \text { April } & \text { May } \\\hline \text { Transporting product } & 2.0 & 3.0 \\\hline \text { Processing product } & 14.0 & 16.0 \\\hline \text { Inspecting product } & 0.5 & 0.8 \\\hline \text { Storing product } & 8.0 & 5.0 \\\hline\end{array} Required:
a.Calculate the manufacturing cycle efficiency for April and May.b.Calculate the processing time required for May so that May's manufacturing cycle efficiency is equal to April's manufacturing cycle efficiency.

Correct Answer:

verifed

Verified

a.April: [14.0/(2.0 + 14.0 + ...