The Satin Manufacturing Company Collected the Following Information (In Days)for

Question 89

Essay

The Satin Manufacturing Company collected the following information (in days)for July and August.  July  August  Transporting product 2.03.0 Processing product 17.018.0 Inspecting product 0.51.2 Storing product 7.07.0\begin{array} { | l | r | r | } \hline & \text { July } & \text { August } \\\hline \text { Transporting product } & 2.0 & 3.0 \\\hline \text { Processing product } & 17.0 & 18.0 \\\hline \text { Inspecting product } & 0.5 & 1.2 \\\hline \text { Storing product } & 7.0 & 7.0 \\\hline\end{array} Required:
a.Calculate the manufacturing cycle efficiency for July and August.b.Assume September's processing time will be the same as August's.If Satin's target for manufacturing cycle efficiency is 65%,what will be September's target for manufacturing cycle time?

Correct Answer:

verifed

Verified

a.July: [17.0/(2.0 + 17.0 + .5...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions