Multiple Choice
The Valenti Company uses flexible budgeting for cost control.Valenti produced 10,800 units of product during October,incurring indirect material costs of $13,000.Its master budget for the reflected indirect material costs of $180,000 at a production volume of 144,000 units.What was the flexible budget variance for the indirect material costs in October?
A) $1,100 favorable.
B) $1,100 unfavorable.
C) $2,000 favorable.
D) $500 favorable.
Correct Answer:

Verified
Correct Answer: