Danske Company Had Total Underapplied Overhead of $15,000 What Is the Fixed Overhead Spending (Budget)variance for May? A)
Question 93
Question 93
Multiple Choice
Danske Company had total underapplied overhead of $15,000.Additional information is as follows: Denominator hours for May Actual hours worked during May Standard hours allowed for May Flexible budget fixed overhead cost Actual fixed overhead costs for May 15,00014,00012,000$45,000$48,000 Variable Overheact Applied based on standard direct labor hours allowed Budgeted based on standard direct labor hours Fixed Overhead: Applied based on standard direct labor hours allowed Budgeted based on standard direct labor hours $42,00038,000$30,00027,000 What is the fixed overhead spending (budget) variance for May?
A) $1,000 unfavorable. B) $3,000 unfavorable. C) $2,000 unfavorable. D) $2,000 favorable.