Tenet Engineering,Inc The Following Information Is Available Concerning Various Activity Measures and the Costs

Question 5

Multiple Choice

Tenet Engineering,Inc.operates two user divisions as separate cost objects.To determine the costs of each division,the company allocates common costs to the divisions.During the past month,the following common costs were incurred:
 Computer servic es ( 85% fixed)  $260,000 Building occupancy 600,000 Personnel costs 110,000 Total common costs $970,000\begin{array} { | l | r | } \hline \text { Computer servic es ( } 85 \% \text { fixed) } & \$ 260,000 \\\hline \text { Building occupancy } & 600,000 \\\hline \text { Personnel costs } & \underline{110,000 }\\\hline \text { Total common costs } & \$ 970,000 \\\hline\end{array} The following information is available concerning various activity measures and service usages by each of the divisions:
 Dirision A Division B  Area occupied (square teet)  20,00040,000 Payroll $380,000$180,000 Computer time (hours)  200220 Computer storage (megabytes)  4,0500 Equipment value $200,000$250,000 Operating profit (pre-allocations)  $565,000$495,000\begin{array} { | l | r | r | } \hline & \text { Dirision } A & \text { Division B } \\\hline \text { Area occupied (square teet) } & 20,000 & 40,000 \\\hline \text { Payroll } & \$ 380,000 & \$ 180,000 \\\hline \text { Computer time (hours) } & 200 & 220 \\\hline \text { Computer storage (megabytes) } & 4,050 & - 0 - \\\hline \text { Equipment value } & \$ 200,000 & \$ 250,000 \\\hline \text { Operating profit (pre-allocations) } & \$ 565,000 & \$ 495,000 \\\hline\end{array} If all common costs are allocated using operating profit as the allocation basis,what is the total cost allocated to Division B?


A) $457,286.
B) $512,714.
C) $555,000.
D) $1,087,576.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge