The Amount of Resources Used in an Activity-Based Costing (ABC)system

Question 44

Multiple Choice

The amount of resources used in an activity-based costing (ABC) system for a specific activity is computed by multiplying the:


A) cost driver rate and the actual cost driver volume.
B) cost driver rate and the planned cost driver volume.
C) overhead rate and the actual cost driver volume.
D) overhead rate and the planned cost driver volume.