Multiple Choice
Denim Products reports the following information about resources.At the beginning of the year,Denim estimated it would spend $84,000 for setups and $41,000 for quality testing.Compute unused resource capacity for quality testing for Denim Products.
A) $4,000.
B) $2,000.
C) $1,000.
D) $5,000.
Correct Answer:

Verified
Correct Answer:
Verified