On May 1,Garage Prefabricators,Inc.,agrees to sell four portable garages to Hiway Truck Service Center.Five days later,Hiway refuses delivery and cancels the contract.Garage Prefabricators is entitled to


A) force Hiway to accept the garage.
B) recover any damages from Hiway but not resell the garage.
C) resell the garage and recover any damages from Hiway.
D) resell the garage but not recover any damages from Hiway.