Multiple Choice
The techniques of project management section of the final report __________.
A) analyzes the impact of organizational structure on the project
B) offers solutions to technical problems that may have occurred
C) reviews the administrative practices used during the project
D) scrutinizes the methods of planning,control,and risk management
Correct Answer:

Verified
Correct Answer:
Verified