Multiple Choice
The __________ section of the audit report contains the auditor's conclusions regarding progress together with recommendations for any changes in technical approach,schedule,or budget that should be made in the remaining tasks.
A) introduction
B) current project status
C) future project status
D) risk management
Correct Answer:

Verified
Correct Answer:
Verified