Multiple Choice
In CPM,__________ are specified.
A) exact levels of uncertainty associated with activities
B) an expected time,a crash time,and the standard deviation time
C) three costs
D) two activity times and two costs
Correct Answer:

Verified
Correct Answer:
Verified