Multiple Choice
Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage,in-process inventory,and __________.
A) resource utilization
B) time utilization
C) management delay
D) schedule utilization
Correct Answer:

Verified
Correct Answer:
Verified