Multiple Choice
Project task E has the following estimates: (1) optimistic time - 10 days,(2) Pessimistic time - 20 days,and (3) Most likely time - 12 Days.The expected time using the beta statistical distribution is __________ days.
A) 13
B) 14
C) 9
D) 22