Multiple Choice
Project task E has the following estimates: (1) optimistic time - 10 days,(2) Pessimistic time - 20 days,and (3) Most likely time - 12 Days.The standard deviation for time using the beta statistical distribution is ________ days.
A) 2
B) 1) 5
C) 2) 33
D) 1) 67
Correct Answer:

Verified
Correct Answer:
Verified