Multiple Choice
Given a project salary cost of $400,000 per year and forecasted wage increases of 5 percent per year,calculate the nondiscounted total salary cost over a three-year project lifecycle.
A) $1,200,000
B) $61,000
C) $1,261,000
D) $1,240,000
Correct Answer:

Verified
Correct Answer:
Verified