Multiple Choice
A work element in the project plan requires 50 hours of labor each by four carpenters.The carpenters are paid $15 per hour and incur an overhead rate equal to 80 percent of their direct labor charges.Based on this data,the appropriate total cost is __________.
A) $2,400
B) $3,000
C) $5,400
D) $4,600
Correct Answer:

Verified
Correct Answer:
Verified