Multiple Choice
____ are where the defined responses to the risks are detailed,but their amounts are not yet precisely known.
A) Known unknowns
B) Unknown knowns
C) Known knowns
D) Unknown unknowns
Correct Answer:

Verified
Correct Answer:
Verified