Multiple Choice
Identify the statement that is NOT a major advantage of placing a project within the pure project organization.
A) The functional manager retains full line authority over project team members.
B) The lines of communication are shortened in regards to the project's resources.
C) Centralized authority tends to increase the speed of decision-making.
D) A holistic approach to performing the project is supported.
Correct Answer:

Verified
Correct Answer:
Verified