Which of the Following Demonstrates the Quality of Flexibility Required

Question 32

Multiple Choice

Which of the following demonstrates the quality of flexibility required of a project selection model?


A) It does not require special interpretation,data that are difficult to acquire,or excessive personnel.
B) It gives valid results within the range of conditions that the firm might experience.
C) It reflects the multiple objectives of both the firm and its managers.
D) It deals with situations both internal and external to the project.

Correct Answer: