Multiple Choice
For a project selected using nonnumeric models,identify the true statement regarding relative priorities for project selection.
A) Operating necessity projects have priority over competitive necessity projects.
B) Competitive necessity projects have priority over operating necessity projects.
C) Operating necessity and competitive necessity projects have equal priority.
D) Product line extension projects have priority over operating necessity projects.
Correct Answer:

Verified
Correct Answer:
Verified