Multiple Choice
Which implemention approach usually entails the greatest level of risk especially if the system is not adequately tested?
A) Direct Cutover
B) Parallel
C) Phased
D) All of the above
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified