Multiple Choice
Completing and settling each contract after any open items or settlements are resolved refers to which of the following Project Procurement Management processes?
A) Plan Procurements
B) Conduct Procurements
C) Administer Procurements
D) Close Procurements
E) Plan Exit Strategy
Correct Answer: