Expected Time to Completion (ETC) is __________
A) how much time it took to complete the work
B) how long we expected the task to take
C) how much time we have left to complete the project
D) how much time it should have taken to complete the task
E) how much longer it will take to complete the project
Correct Answer:

Verified
Correct Answer:
Verified