Multiple Choice
If we know the Actual Cost of a WBS component, what other value do we need to know in order to calculate the cost performance index (CPI) ?
A) Budget at Completion (BAC)
B) Budget costs of remaining work (BCRW)
C) Schedule Variance (SV)
D) Expected Time Complete (ETC)
E) Earned Value (EV)
Correct Answer: