Multiple Choice
The metric that provides an estimate of the most likely total or final cost of the project based on the project's performance and any risks that should be considered is the:
A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
Correct Answer:

Verified
Correct Answer:
Verified
Q55: Earned value provides a performance measurement that
Q56: Budget At Completion (BAC) is the total
Q57: All of the project stakeholders should receive
Q58: Generally, the more metrics one adopts, the
Q59: If we know the Actual Cost of
Q61: Information distribution includes all of the following
Q62: Why is effective and efficient communication vital
Q63: Planned value (PV) is the planned or
Q64: How is the Schedule Performance Index calculated
Q65: Explain the concept of Earned Value and