Multiple Choice
_____ involves development of a risk management plan.
A) Plan Risk Management
B) Identify Risks
C) Perform Quantitative Risk Analysis
D) Plan Risk Responses
E) Monitor and Control Risks
Correct Answer:

Verified
Correct Answer:
Verified