Solved

Which of the Following Statements About the Work Breakdown Structure

Question 11

Multiple Choice

Which of the following statements about the work breakdown structure WBS) is not ?


A) The WBS provides a hierarchical structure that outlines the activities or work that needs to be done in order to complete the project scope.
B) The WBS should support the project's MOV
C) The WBS should be developed by the project manager.
D) The WBS provides a framework for developing a tactical plan to structure the project work.
E) The WBS provides a bridge or link between the project's scope and the detailed project plan

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions