Multiple Choice
Which of the following statements about the work breakdown structure WBS) is not ?
A) The WBS provides a hierarchical structure that outlines the activities or work that needs to be done in order to complete the project scope.
B) The WBS should support the project's MOV
C) The WBS should be developed by the project manager.
D) The WBS provides a framework for developing a tactical plan to structure the project work.
E) The WBS provides a bridge or link between the project's scope and the detailed project plan
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Describe bottom-up estimating.What are some advantages and
Q6: Under the COCOMO model,describe the organic,semi-detached,and embedded
Q9: _ focuses on the processes,tools,and methods for
Q13: LOC in a software application program<br>A)can be
Q14: A management report and its accompanying graphs
Q20: _ is the most common, real-world method
Q24: Confidence in project estimates will be highest
Q37: _ can be a very effective estimating
Q41: What is guesstimating? Why should a project
Q81: Each phase of the project should provide