menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Technology Project Management Study Set 1
  4. Exam
    Exam 5: Project Planning: Scope and the Work Breakdown Structure
  5. Question
    In the WBS Context, a Crux Is Best Described by Which
Solved

In the WBS Context, a Crux Is Best Described by Which

Question 57

Question 57

Multiple Choice

In the WBS context, a crux is best described by which of the following:


A) a risk metric
B) a phase gate
C) evidence of a phase completion
D) a deliverable
E) a proof of concept

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q52: The concept of actors is an integral

Q53: Why is important to ensure that the

Q54: Describe product-oriented scope and the tools that

Q55: Scope grope suggests a fundamental and significant

Q56: The first step in accurately estimating an

Q58: One way to ensure that the WBS

Q59: What is the relationship between the project's

Q60: A tangible and verifiable piece of work

Q61: What is a work breakdown structure (WBS)?

Q62: The work breakdown structure (WBS) decomposes, or

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines