Multiple Choice
_____ can be a very effective estimating technique by forcing examination of project risks so that specific budget or schedule targets can be achieved.
A) Guesstimating
B) Delphi Technique
C) Time Boxing
D) Top-Down Estimating
E) Bottom-Up Estimating
Correct Answer:

Verified
Correct Answer:
Verified