Multiple Choice
Which of the following processes of Scope Management Process defines what work will and will not be included in the project?
A) Collect Requirements
B) Define Scope
C) Create Work Breakdown Structure
D) Verify Scope
E) Control Scope
Correct Answer:

Verified
Correct Answer:
Verified