Multiple Choice
Which of the following processes of Scope Management Process ensuring that controls are in place to manage proposed scope changes once the project's scope is accepted?
A) Collect Requirements
B) Define Scope
C) Create Work Breakdown Structure
D) Verify Scope
E) Control Scope
Correct Answer:

Verified
Correct Answer:
Verified