Multiple Choice
According to the PMBOK,there are four processes associated with Project Human Resources Management.The process that ensures the tracking of the project team's performance,providing feedback,resolving interpersonal issues,and managing organizational change is:
A) Develop Human Resources Plan
B) Acquire Project Team
C) Develop Project Team
D) Manage Project Team
E) Control Project Team
Correct Answer:

Verified
Correct Answer:
Verified
Q2: The Functional Organization is based upon organizing
Q18: Describe the roles of a project manager.
Q24: The main feature of the Matrix Organizational
Q26: Disadvantages of the Project Organizational structure include
Q33: The project environment includes not only the
Q39: High level of integration,improved communication,and increased project
Q43: In conducting a stakeholder analysis,why is it
Q45: The structure that reveals most clearly how
Q67: Describe the matrix organizational structure.
Q70: Which of the following attributes is least