Multiple Choice
The documenting and archiving of all project documents and evaluating the project in terms of MOV is the definition of:
A) Contract closure
B) Administrative closure
C) End phase evaluation
D) Project history
E) Final phase management
Correct Answer:

Verified
Correct Answer:
Verified