Multiple Choice
The _____ details how quality planning, assurance, and control will be supported throughout the project life cycle.
A) Communications Plan
B) Scope Management Plan
C) Quality Management Plan
D) Change Management Plan
E) Human Resources Plan
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q51: Briefly describe the nature of the formal
Q52: What are the goals and purposes of
Q53: What is the focus of project administration
Q54: What is the project environment? Why must
Q55: What is the relationship between an organization's
Q57: The Project Organization is based upon organizing
Q58: Constraints can be thought of as things
Q59: Assumptions can be thought of as things
Q60: What is Project Scope and how should
Q61: Describe the project organizational structure.