Multiple Choice
Trying to decide between three alternatives,a company employed a scoring model.Three criteria were chosen.Criteria A was believed to be the most important and so was given a weight of 50%.The other two were deemed to be equal to each other in importance.A relative scoring range of 0 to 10 was used.The table below shows each alternative and their scores.Which alternative should the company choose?
A) Choose alternative A
B) Choose alternative B
C) Choose alternative C
D) Choose either alternative A or B
E) Choose either alternative A or C
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A business case is a deliverable that
Q3: For the sake of efficiency and unity
Q4: A project that provided cleaner air would
Q5: Evaluating the feasibility of an alternative in
Q5: Evaluating the feasibility of an alternative in
Q16: What is a project infrastructure?
Q18: An Information Technology Project Methodology ITPM )<br>A)is
Q20: Feasibility focuses on whether a particular alternative
Q22: _ focuses on carrying out the project
Q34: The net present value method of project