Essay
During the most recent month at Luinstra Corporation, queue time was 4.5 days, inspection time was 0.8 day, process time was 1.9 days, wait time was 5.1 days, and move time was 0.7 day.
Required:
a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent in non-value-added activities?
d. Compute the delivery cycle time.
Correct Answer:

Verified
a. Throughput time
= Process time + Insp...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
= Process time + Insp...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q101: Daab Products is a division of a
Q102: Suppose a company evaluates divisional performance using
Q103: A disadvantage of using ROI to evaluate
Q104: Aguilera Industries is a division of a
Q105: Which of the following performance measures will
Q107: The West Division of Frede Corporation had
Q108: Residual income is the net operating income
Q109: For the past year, Allargando Company recorded
Q110: A cost center is not a responsibility
Q111: Consider the following three conditions: I. An