Goldman Corporation uses time and material pricing. The repair department expects 20,000 direct labor hours of activity and has the following selected data: The company's time charge per hour is:
A) $11.
B) $24.
C) $40.
D) $64.
E) $75.
Correct Answer:

Verified
Correct Answer:
Verified