Bushnell, Inc. has a standard variable overhead rate of $4 per machine hour, with each completed unit expected to take three machine hours to produce. A review of the company's accounting records found the following:
Actual variable overhead: $210,000
Variable-overhead efficiency variance: $18,000U
Variable-overhead spending variance: $30,000F
How many units did Bushnell actually produce during the period?
A) 13,500.
B) 16,500.
C) 18,500.
D) 21,500.
E) None of the other answers are correct.
Correct Answer:

Verified
Correct Answer:
Verified
Q22: What is the most common treatment of
Q42: Riskless Insurance uses budgets to forecast and
Q43: Draco, Inc. has the following overhead standards:<br>Variable
Q44: A production manager was recently given a
Q45: Alexandria Corporation applies fixed manufacturing overhead to
Q48: Jackson Corporation uses a standard cost system,
Q50: Robert Company, which applies overhead to production
Q73: In an effort to reduce record-keeping, companies
Q84: Briefly describe the procedures that are used
Q87: The activity measure selected for use in