Question 11

Essay

Chambliss Corporation has three costs: A, which is variable; B, which is fixed; and C, which is semivariable. The company uses the high-low method and extracted the following data from its accounting records:
• At 180,000 hours of activity, Cost A totaled $2,610,000.
• At 140,000 hours, the low point during the period, Cost C totaled $1,498,000; at 200,000 hours, the high point, Cost C's fixed portion amounted to $1.75 per hour.
• At 160,000 hours of activity, the sum of Costs A, B, and C amounted to $8,162,000.
Required:
A. Compute the variable portion (total) of Cost C at 140,000 hours of activity.
B. Compute Cost C (total) at 160,000 hours of activity.
C. Compute Cost B (total) at 160,000 hours of activity.

Correct Answer:

verifed

Verified

A. Cost C's fixed portion will total the...